Eversource/Neurrco recently did work on the street and they paved up areas that they had repaired. As a result, the paving is a mound and not smooth causing stall water to remain from rain. This is causing a backup of water on the street and now with colder temps causing an ice back up because the water can't flow.
Remedy would be to even out or level patch paving on street in between 7 and 9 Van Norden
6 Comments
City of Cambridge (Verified Official)
DG (Registered User)
Public Works - TS (Streets & Sewers) (Verified Official)
Public Works - PA (Inspections) (Verified Official)
ESG- Neucco to mill and overlay paving trench this spring 2024
Acknowledged Public Works - PA (Inspections) (Verified Official)
-ESG to mill and overlay trenches this spring 2024
Closed Public Works - PA (Inspections) (Verified Official)
ESG sub restored trench (partial paving )